1 min agoBakersfield Hires Willdan To Install 133 EV Chargers For City Fleet 4 min agoTower Hamlets Appoints TotalEnergies To Install 1,500 On-Street EV Chargers 18 min agoItaly Approves €897M For 59 Water Security Projects In Second Tranche Of National Plan 21 min agoSTASY Awards Dotsoft €1.09M Contract For Smart Parking At Four Athens Metro Stations 24 min agoSensoneo Builds Central IT System For Greece’s DRS Hellas Deposit Return Scheme 7h agoISPRA Awards CAE a Contract To Run Italy’s National Tide-Gauge Network 7h agoMetrify Offers To Run Smart Meter Rollouts For German Stadtwerke With A Right To Take Them Back 7h agoBrussels Grid Operator Picks Solutions30’s Unit-T To Install Up To 18,000 Smart Meters A Year 7h agoBloomfield Adds 14 Bigbelly Smart Bins To Its Rodent Control Effort 7h agoSpain Centralises Data From Over 4,000 Hydrological Sensors In GOTA Water Observatory
Kurrantly News · Weekly briefingThe week in smart cities and utilities, in one email
Share
EV Charging · USA

Bakersfield Hires Willdan To Install 133 EV Chargers For City Fleet

The California city is moving to avoid fines of up to $10,000 a day under state zero-emission rules for public agency vehicle fleets.

Kurrant News Desk · ·3 min read
A row of white pedestal EV chargers with plugged cables beside blue-marked parking bays, a silver car parked behind them

Bakersfield City Council voted on 18 November 2026 to hire Willdan, an Anaheim-based energy and engineering services firm, to build electric vehicle charging at eight city-owned properties, The Bakersfield Californian reported. The not-to-exceed contract is worth $19.92 million and passed unanimously, with two council members absent.

Bakersfield, a city of about 403,000 residents in California’s Kern County, is preparing the charging network for a municipal fleet that has to switch to zero-emission vehicles.

Why: A State Rule For Public Fleets

The contract responds to the California Air Resources Board’s Advanced Clean Fleets regulation for state and local government fleets. Under the rule, half of these fleets’ vehicle purchases had to be zero-emission from 2024, rising to all purchases from 2027.

About 400 city vehicles are affected, according to KGET. City staff told the council that non-compliance could bring daily fines and holds on vehicle registrations.

Several council members questioned the mandate while voting for the contract. “It is very unfortunate that the state is putting this burden of an unfunded mandate on us, but we are where we are,” said Karen Goh, Mayor of Bakersfield, at the meeting, as reported by KGET.

How The Contract Is Structured

The contract covers 133 chargers plus make-ready ports, which are wired positions for chargers to be added later.

Before the vote, Willdan carried out an investment-grade audit of the city’s charging needs. The audit projects a cost of $8.8 million to move the fleet to electric vehicles and $26 million in savings over 20 years, including maintenance and replacement, figures from Willdan’s own analysis.

Willdan guarantees $331,000 in energy savings in the first year and has agreed to pay the city any shortfall, according to the Californian. The contract includes measurement and verification of actual savings and rules out change orders unless the city requests extra work. The city projects $1.1 million in operational savings in the first year.

The city is paying from its own funds without borrowing. City documents cited by KGET list about $4.6 million from the equipment fund, $8.3 million from the solid waste fund, $4.3 million from the wastewater fund and $1.7 million from the domestic water fund.

Earlier Willdan Deals And Comparable Contracts

Bakersfield’s earlier dealings with Willdan were mixed. In August 2026 the council rejected a $9.2 million Willdan energy savings contract that combined solar canopies, a battery and EV charging at the city’s Water Resources building. A revised solar and battery project for the same building, without the chargers, was approved later.

Other California public agencies are buying for the same rule at different scales. Laguna Beach approved about $4.7 million in contracts with PowerFlex for 42 chargers, and San Diego signed a $112 million energy savings contract with Willdan covering 23 buildings and about 39,000 streetlights.

What Happens Next

Construction is due to finish by the end of 2027, the year from which all new vehicles bought by public fleets in California must be zero-emission. The contract also leaves 136 make-ready ports for chargers to be added as more of the fleet is replaced.