Severn Trent, the water and wastewater company serving 4.6 million customers in the Midlands, said on 18 November 2026 that it now expects capital investment of £2.3 billion to £2.5 billion in the year to March 2027. The previous range was £2.2 billion to £2.5 billion, according to its half-year financial report.
The company said all its other guidance and outlook were unchanged. Revenue rose 7% to £1.54 billion in the six months to 30 September 2026.
Why: The Largest Programme In Its History
The spending comes from the 2025-2030 regulatory period, known as AMP8. In December 2024, Ofwat set Severn Trent a total expenditure allowance of £15 billion for the five years, £8 billion more than in 2020-2025.
More than £2 billion of that is for river health and cutting spills from storm overflows, according to the company. It also has a £420 million project to lay 865 miles of new water mains, with smart water meters fitted in areas where pipes are upgraded.
For suppliers, the pace of contracting is the key figure. Severn Trent said 65% of the AMP8 programme is now in contract and expects that share to reach 80% by March 2027. Half of its enhancement projects are in construction.
Smart Meters, Mains And Overflows
Severn Trent said it has delivered 45% of its commitment to install one million smart meters. As we reported in September 2025, it appointed Netmore Group to deploy and manage the advanced metering network for that rollout under a £200 million contract.
Capital investment in the first half was £1.05 billion, up 36.9% from £769 million a year earlier. The company renewed 376 km of water mains, 27% of its 2030 target.
It said it is on track to meet its regulatory target of no more than 18 average spills per storm overflow this year. It also expects to meet its leakage target of 334.6 megalitres a day for a ninth consecutive year, after two years of record demand.
Severn Trent reported £250 million of capital efficiencies, which it says is half its AMP8 target. It said it has secured at least £402 million through regulatory reopeners, including £51 million of funding within the current period, at draft stage.
What Happens Next
The company expects 80% of the AMP8 programme to be in contract by March 2027, which leaves about a fifth of the five-year spend still to be procured.
Other English water companies are also buying at scale for AMP8. As we reported on 8 November 2026, Thames Water has gone to tender for a smart metering programme valued at £1.58 billion including VAT.