ORES, the distribution system operator that runs most of Wallonia’s electricity network, has confirmed a fault in part of its fleet of communicating electricity meters, RTL Info reported on 18 November 2026. The operator detected the problem in mid-September 2026, and a joint smart metering committee reviewed it in early November, according to BeProsumer, a Belgian site for households that produce their own power.
Why: Wrong Registers Under New Time-Of-Use Tariffs
ORES and RESA told BeProsumer that the meter memory could be disrupted during calendar operations, when a meter switches between tariff periods. In their words, kWh “can then be added to the wrong index while the total consumption remains correct”.
The timing matters for bills. Since 1 January 2026, Walloon households have had a new off-peak slot from 11:00 to 17:00 and an optional three-band network tariff. The split between registers now sets part of what they pay.
Prosumers are exposed too. ORES has about 300,000 of them, and their net-metering compensation, which depends on correct injection readings, runs until 31 December 2030.
A Joint Fault With RESA
The problem is shared with RESA, the operator for the Liège area. RESA gave BeProsumer a combined figure, prepared with ORES, of 11,308 affected meters across both networks on 12 November 2026.
BeProsumer identified the affected units as IBM and Sagemcom devices. ORES’s own single-phase customer brochure lists Siconia S211 and Siconia XS212 meters alongside the Landis+Gyr E360-1P.
The two operators have started corrections and replacements. The number of meters to be swapped depends on how many remain faulty after correction.
The ORES share of the fault equals about 2% of its communicating fleet. ORES had 429,272 such meters at the end of 2025, about 28% of its low-voltage meters, according to figures the Walloon energy minister gave the regional parliament.
Earlier Faults And A Regulator’s Fine
ORES has faced other metering problems this year. On 3 April 2026, the Walloon energy regulator CWaPE fined ORES Assets €23,000, cut from a proposed €46,000, for failing to update the balance shown on communicating prepayment meters.
That fault followed IT changes in June 2025 and peaked at about 5,400 first-generation meters. In January 2026, some communicating meters in areas without mobile coverage also missed the switch to the new off-peak hours, Energie Info Wallonie reported.
Elsewhere in Europe, Ireland’s ESB Networks replaced about 27,000 meters in 2016 after finding a component that could fail and overcharge customers.
What Happens Next
The mass rollout began on 15 September 2025, with up to 300,000 meters a year installed by Enzo, a consortium of Infra Group, APK Group, Circet and Kobor. ORES and RESA are due to replace about 1.5 million meters by 31 December 2029, L’Avenir reported.
ORES set itself a target of 260,000 more communicating meters in 2026, and about 700,000 are projected across Wallonia by the end of the year.