1 min agoDijon Métropole Tenders 10-Year Rental And Remote Reading Of City Water Meters 1 min agoBenidorm Tenders Final €2.38M Phase Of Paseo De Levante Lighting And Catenary Renewal 5 min agoEsyasoft Completes £36.5M Takeover Of Smart Meter Communications Firm CyanConnode 8 min agoNorth Of Scotland Councils Open First New Site Under 20-Year EV Charging Partnership With EZO 12 min agoDEW21 And DOGEWO21 Add 28 Public Charge Points At 14 Dortmund Housing Estates 16 min agoWarsaw Start-Up WaterSense Raises €5.75M For River Pollution Forecasting Sensors 29 min agoSão José Dos Pinhais Picks SJP Inteligente For 22-Year PPP Covering 40,000 Streetlights YesterdayEridanis Acquires Citégestion, EDF’s Urban Asset Management Software Subsidiary YesterdayCanal de Isabel II Signs €1.15M Five-Year NB-IoT Meter Connectivity Contract With Telefónica YesterdayEU Requires Card Payment Retrofit On Older 50 kW-Plus Public Chargers From 1 January 2027
Kurrantly News · Weekly briefingThe week in smart cities and utilities, in one email
Share
Street Lighting · Spain

Benidorm Tenders Final €2.38M Phase Of Paseo De Levante Lighting And Catenary Renewal

The 1990s seafront columns get LED, DALI point-to-point telemanagement and housings for WiFi, mobile repeaters and CCTV power supplies.

Kurrant News Desk · ·3 min read
Lit lamp posts along an empty seafront promenade at dusk, with a breakwater and the Mediterranean behind

Benidorm City Council, which governs the Costa Blanca resort of 77,221 residents in Alicante province, approved the start of the tender for the third and last phase of the project on 23 November 2026, DS Alicante reported. Bids are due by 21 December, and the works have a five-month execution period.

Why: A Corroded Installation The City Says The State Should Fund

The lighting and ornamental catenary along Paseo de Levante date from the 1990s and were built by Spain’s then Ministry of Public Works. More than three decades on the seafront have left them corroded and worn, and the promenade sits in the coastal public domain, so the coastal authority, Costas, had to authorise the project before the documents were drafted.

The council approved the phase III project on 14 September 2026 and is paying for it from its own budget. “We are talking about a work that the State would be responsible for financing and carrying out,” Mayor Toni Pérez said at the time, as reported by El Periòdic.

Kurrant Tender Tracker

This project is heading to tender

New street lighting tenders worldwide, flagged daily with an AI summary.

Get street lighting tender alertsGet tender alerts

The first phase, between Plaza del Torrejó and Avenida de Europa, ran from December 2022 to spring 2023 at a cost of €1.97 million in municipal funds. The second phase, up to Calle Metge Miguel Martorell, was awarded to Elecnor, the Spanish engineering and installation group, in March 2025 for €854,885.07, funded by NextGenerationEU money through the city’s tourism sustainability plan.

What The Final Phase Replaces

Phase III covers columns 60 to 99, between Avenida Filipinas and the end of Avenida de Madrid, fed from three control cabinets. The new 14-metre columns keep the promenade’s twelve-sided design, in high-strength steel with a galvanised and powder-coated finish rated for marine environments, Smart Lighting reported.

The project swaps 400 W metal halide promenade lamps for 106 W LED luminaires, and 400 W high-pressure sodium beach floodlights for two 220 W LED floodlights per column. The 32 W fluorescent lanterns on the catenary give way to 25 W RGB LED units that can change colour and run programmed scenes.

The project calculates that installed power falls by 36.16 kW, or 37.86%, on this stretch.

A point-to-point telemanagement system must connect to the municipal platform. Its nodes must use the DALI protocol so that luminaires from different manufacturers can be dimmed, monitored and metered remotely.

Concrete benches attached to the columns are to house the junction boxes, which now sit by the beach wall and suffer from storms and corrosion. Every two or three columns, a radome-style housing is to hold equipment for city services such as WiFi access points, 4G and 5G repeaters or power for municipal CCTV cameras.

How Bids Are Scored

Price carries up to 60 points. Technical criteria judged by the panel carry up to 40, of which 8 points go to the telemanagement system and 10 to the supply and works programme.

What Happens Next

Bids close on 21 December 2026, and the five-month works period starts once the contractor and the council sign the site verification record.

The phase II tender drew two bidders: Elecnor scored 95 points and SICE 82.69.