The Swiss Federal Roads Office (FEDRO) said on 23 November 2026 that it has awarded three lots of fast-charging sites for electric heavy goods vehicles on the national roads, Keystone-SDA reported. FEDRO received eleven applications during the four-month call, which ran from 5 January to 30 April 2026.
Why: A Target Of 82 Truck Charging Stations By 2035
FEDRO places the programme under the federal Energy Strategy 2050 and the transport ministry’s electromobility roadmap. Its target is 82 fast-charging stations for trucks along the national roads by 2035.
Electric trucks are gaining share. Battery-electric vehicles accounted for 847 new registrations above 3.5 tonnes from January to September 2026, a 27.4% share, according to importers’ association auto-schweiz figures cited by Fastned.
Track tenders like this
New smart mobility tenders worldwide, flagged daily with an AI summary.
The heavy vehicle fee also favours electric trucks for now. They are exempt until the end of 2030. Parliament voted on 2 October 2026 to phase the fee in from 2031 with a 70% discount, falling to 10% in 2035 and to zero from 2036, electrive reported. The referendum period on that law is still running.
Operators Finance The Stations, FEDRO The Grid Link
Fastned, a Dutch fast-charging operator, won lot 1 with 11 sites. Obornes, based in Aix-en-Provence, France, won lot 2. Milence, the truck charging joint venture of Daimler Truck, Traton and Volvo Group, won lot 3 and says it has 11 sites.
The awards are reservation agreements, with no payment from FEDRO. Operators plan, finance, build, run and maintain the stations without subsidies. FEDRO builds and pre-finances the grid connection up to and including the transformer station, and operators repay it through an annual compensation payment.
The call fixed the number of charge points at each site, electrive reported. They range from two CCS points at Campagnola to two Megawatt Charging System (MCS) points and ten CCS points at the Rothenburg heavy-vehicle control centre. Seven sites have at least one MCS point, and CCS points must deliver at least 350 kW. Bids were rated mainly on construction quality and energy efficiency.
How It Compares
The model follows FEDRO’s 2018 call for car fast charging at 100 rest areas, awarded in five packages of 20. More than half of those sites were equipped by August 2026, according to FEDRO.
Germany is building on a larger scale. Autobahn GmbH awarded 836 truck charge points, 447 of them MCS, at 124 unstaffed rest areas on 1 July 2026. It launched a tender for 220 staffed rest areas in November 2026. In the EU, the AFIR regulation requires truck charging pools every 60 km on the TEN-T core network by 2030.
What Happens Next
Operators have two years to plan the sites and file building permits. The first stations are due to open in 2030, and the 32 sites awarded cover 39% of the 82-station target.