1 min agoSwitzerland Awards 32 Motorway Charging Sites For Electric Trucks To Fastned, Obornes And Milence 6 min agoMexico City Plans MXN 1B (€47M) First Phase Of Adaptive Traffic Signals 16 min agoZagreb Builds Citywide LoRaWAN Network With 650 Gateways For Utility Meter Reading YesterdayOn Charge Opens First Of 11 Privately Funded Charging And Security Hubs In Rome 22 NovSan José Hires Verra Mobility To Run 33-Site Speed Camera Pilot 22 NovOhio Commits $31M In Federal NEVI Funds To 40 New EV Fast-Charging Sites 22 NovAustralian Energy Regulator Lets Essential Energy Own 300 Streetlight EV Chargers In Regional NSW 22 NovAutobahn GmbH Tenders 3,120 E-Truck Charge Points At 227 Serviced Motorway Rest Areas 21 NovColumbia, Missouri To Start Smart Meter Installs In Spring 2027, Funded By Special Obligation Bonds 21 NovEDF Agrees To Buy Utilita Owner Luxion, Adding 1.3 Million UK Energy Accounts
Kurrantly News · Weekly briefingThe week in smart cities and utilities, in one email
Share
EV Charging · Switzerland

Switzerland Awards 32 Motorway Charging Sites For Electric Trucks To Fastned, Obornes And Milence

Operators fund, build and run the stations without subsidy, and the first ones are due to open in 2030 at rest areas and control centres.

Kurrant News Desk · ·2 min read
Row of fast chargers with cables beside a parking area where trucks and a container lorry stand in sunlight

The Swiss Federal Roads Office (FEDRO) said on 23 November 2026 that it has awarded three lots of fast-charging sites for electric heavy goods vehicles on the national roads, Keystone-SDA reported. FEDRO received eleven applications during the four-month call, which ran from 5 January to 30 April 2026.

Why: A Target Of 82 Truck Charging Stations By 2035

FEDRO places the programme under the federal Energy Strategy 2050 and the transport ministry’s electromobility roadmap. Its target is 82 fast-charging stations for trucks along the national roads by 2035.

Electric trucks are gaining share. Battery-electric vehicles accounted for 847 new registrations above 3.5 tonnes from January to September 2026, a 27.4% share, according to importers’ association auto-schweiz figures cited by Fastned.

Kurrant Tender Tracker

Track tenders like this

New smart mobility tenders worldwide, flagged daily with an AI summary.

Get smart mobility tender alertsGet tender alerts

The heavy vehicle fee also favours electric trucks for now. They are exempt until the end of 2030. Parliament voted on 2 October 2026 to phase the fee in from 2031 with a 70% discount, falling to 10% in 2035 and to zero from 2036, electrive reported. The referendum period on that law is still running.

Operators Finance The Stations, FEDRO The Grid Link

Fastned, a Dutch fast-charging operator, won lot 1 with 11 sites. Obornes, based in Aix-en-Provence, France, won lot 2. Milence, the truck charging joint venture of Daimler Truck, Traton and Volvo Group, won lot 3 and says it has 11 sites.

The awards are reservation agreements, with no payment from FEDRO. Operators plan, finance, build, run and maintain the stations without subsidies. FEDRO builds and pre-finances the grid connection up to and including the transformer station, and operators repay it through an annual compensation payment.

The call fixed the number of charge points at each site, electrive reported. They range from two CCS points at Campagnola to two Megawatt Charging System (MCS) points and ten CCS points at the Rothenburg heavy-vehicle control centre. Seven sites have at least one MCS point, and CCS points must deliver at least 350 kW. Bids were rated mainly on construction quality and energy efficiency.

How It Compares

The model follows FEDRO’s 2018 call for car fast charging at 100 rest areas, awarded in five packages of 20. More than half of those sites were equipped by August 2026, according to FEDRO.

Germany is building on a larger scale. Autobahn GmbH awarded 836 truck charge points, 447 of them MCS, at 124 unstaffed rest areas on 1 July 2026. It launched a tender for 220 staffed rest areas in November 2026. In the EU, the AFIR regulation requires truck charging pools every 60 km on the TEN-T core network by 2030.

What Happens Next

Operators have two years to plan the sites and file building permits. The first stations are due to open in 2030, and the 32 sites awarded cover 39% of the 82-station target.