1 min agoAutobahn GmbH Tenders 3,120 E-Truck Charge Points At 227 Serviced Motorway Rest Areas 20h agoColumbia, Missouri To Start Smart Meter Installs In Spring 2027, Funded By Special Obligation Bonds 21h agoEDF Agrees To Buy Utilita Owner Luxion, Adding 1.3 Million UK Energy Accounts YesterdayNatal Starts Installing Adaptive Traffic Signals On Avenida Prudente De Morais YesterdayBrightAI Raises $97M At Reported $750M Valuation, With GE Vernova As Investor YesterdaySlovak Road Administration Renews Vaisala Road Weather Station Maintenance YesterdayKnoxville Police Start Flying Skydio Drones To 911 Calls From 12 Docks YesterdayNational Measurement Institute Approves Itron Streetlight Controllers For Type 9 Metering YesterdayUK Government Commercial Agency Adds Pelion To £1.5B Mobile Services Framework YesterdayMaddalena Names Biesenthal Exclusive Distributor For German Water Utilities
Kurrantly News · Weekly briefingThe week in smart cities and utilities, in one email
Share
EV Charging · Germany

Autobahn GmbH Tenders 3,120 E-Truck Charge Points At 227 Serviced Motorway Rest Areas

The second round of Germany's federal truck charging network brings the plan to about 4,000 points at 351 motorway sites, sized to EU AFIR rules.

Kurrant News Desk · ·3 min read
Row of high-power charging units with cables beside a parking area where lorries and a container truck are parked

Die Autobahn GmbH des Bundes, the federal company that runs Germany’s motorways, said on 18 November 2026 that it has launched an EU-wide procedure to find operators to plan, build and run public fast charging for battery-electric trucks at serviced rest areas, acting for the Federal Ministry of Transport (BMV). The plan covers about 1,251 Megawatt Charging System (MCS) points and 1,869 CCS points, according to the Autobahn GmbH announcement.

Why The Federal Government Is Building Truck Charging

The EU’s alternative fuels infrastructure regulation, AFIR, requires heavy-duty charging pools of at least 3,600 kW every 60 km on the core TEN-T road network by the end of 2030. Autobahn GmbH says it chose the sites with the national charging infrastructure office, taking account of AFIR minimums, freight traffic flows, space at each site and planned private charging.

Truck makers face EU CO2 targets of 45% below 2019 levels for new heavy vehicles by 2030. Germany has also extended the toll exemption for zero-emission trucks to 30 June 2031.

Kurrant Tender Tracker

This project is heading to tender

New smart mobility tenders worldwide, flagged daily with an AI summary.

Get smart mobility tender alertsGet tender alerts

Demand is still small. About 4,200 electric trucks over 3.5 tonnes were registered in Germany in 2025, an 11.7% share of new trucks and the highest in the EU, according to Eurostat data reported by electrive. Manufacturers surveyed by the federal agency NOW expect battery trucks to reach about half of new registrations in 2035.

How The Tender Works

The procedure has five lots of about 45 rest areas each, mixing larger and smaller sites. Bidders may bid for every lot but can win only one, according to the project brief. Companies first apply to take part, and qualified applicants are then invited to submit initial offers.

The prior information notice sets minimum power of 1 MW for MCS points and 400 kW for CCS points used during breaks, with 150 kW CCS points for overnight charging. Contracts run for eight years with options of up to four more, and the build-out is due within five years, depending on grid connections.

The federal government pays for the grid connections. It sets one infrastructure fee for all lots, which operators collect on every charge and pass back to the state, while any margin above it stays with the operator. Operators carry the risk on availability, power purchasing and sales.

The First Round At Unserviced Sites

The new tender follows contracts awarded on 30 June 2026 for 124 unserviced rest areas, which have parking and toilets but no fuel station or restaurant. The five winners were eliso Voltix Charging; autostrom.plus; Electric Mobility Infrastructure Deutschland, part of Engie Vianeo; a STRABAG-led consortium with charging firms eLoaded and R:loaded; and a consortium of E.ON Drive and Tank & Rast unit mblty.

That round covers 836 charge points, 447 of them MCS, according to the ministry. The European Commission approved up to €1.6 billion in state aid for that scheme in December 2025.

What Happens Next

Requests to participate are due by 5 January 2027, according to the published notice. Negotiations are planned for April to June 2027, and the contracts are set to start on 1 October 2027.